The East Greenbush Central School District has selected contractors for Phase 1A of the Capital Project through a public competitive bidding process. The total bid amount for Phase 1A, which includes the CHS tennis courts, basketball courts and roof, came in under budget by approximately $1.1 million. Those savings will provide more flexibility with items later in the project (e.g., air conditioning in elementary schools).
The contractors selected are Niko K. Construction Corp. and M. Sullivan Construction.
The bids were recommended by the district’s architect LaBella Associates and construction manager Turner Construction, and then approved by the Board of Education at their public meeting on Wednesday evening.
Pending weather, construction will begin April 14 (tennis courts), April 21 (basketball courts), and May 12 (roof).
Bid Results
For more information about the Capital Project, visit www.egcsd.org/capitalproject.