Construction has begun for the renovation of Howard L. Goff Middle School’s library.
Progress continues on the East Greenbush Central School District’s Capital Project “Building a Brighter Future.” During Winter Recess in February, contractors began installation of the new sewer and sanitary lines beneath Red Mill. This work was added to the capital project in December based on the failing condition of the school’s plumbing and its impact on school operations.
Additionally, construction in the Goff Middle School library has begun. That space will be completely renovated this year to provide an improved learning environment for our students. A temporary library space has been created in the school cafeteria so those services will continue.
Phase 1B
- Construction for Phase 1B, which includes the Goff athletic fields and access road, continues through this spring and summer
Phase 2
- Goff
- Goff library construction began during Winter Recess
- Red Mill
- Sewer and sanitary lines installed beneath Red Mill
- Red Mill playground construction will begin during Spring Recess
- Red Mill library construction will begin in December 2026
For more information about the Capital Project, visit www.egcsd.org/capitalproject.