Capital Project

The East Greenbush CSD has proposed a $116 million capital project that, if approved by voters, would improve facilities and grounds at all seven schools at no additional cost to the local taxpayer. The proposed capital project will be a proposition on the School Budget Vote and Board Election ballot scheduled for Tuesday, May 21, 2024.

Video | Infographic | More Information

Select Page
Red Mill gymnasium

Refinished gym floor at Red Mill.

The East Greenbush Central School District would like to provide an update on the Capital Project that was approved in 2017. To date, all of the major health and safety priority items have been completed at all schools, including new fire alarm and carbon monoxide systems, new security cameras, a new card access entry system and a new public address system.

This past summer, several bathrooms were renovated at Green Meadow, Red Mill and Goff to make them ADA compliant. New cabinetry was installed in classrooms at Green Meadow and Red Mill where bathrooms were enlarged. The gym floors at Green Meadow and Red Mill were refinished and new domestic hot water heating systems were replaced. Similar projects will be completed at other district schools next summer.

A full list of the Capital Project and the status of specific items can be found below.

New PA system speaker with digital clock

Public address system and clock units.

Completed Projects

  • Card Access and Key Entry Systems – District-wide
  • Security Cameras – District-wide
  • Public Address Systems – District-wide
  • Telephone Systems – District-wide
  • Asbestos Abatement – District-wide (ongoing with projects)
  • Wireless Access Points – District-wide
  • Fire Alarm System – District-wide
  • Refinished Gym Floors – Green Meadow and Red Mill
  • Replacement of original small toilet rooms in classrooms with code compliant toilet rooms, including associated abatement, supply and waste piping, fixtures, replacement of affected adjacent cabinetry in classrooms, finishes, etc. – Green Meadow and Red Mill (ongoing at Green Meadow and Red Mill)
  • Re-roofing of older sections of roof membrane – Red Mill
  • Reconstruction of service and north area paving – Red Mill
  • Replacement of hot water heating system – Green Meadow, Red Mill and Goff
  • Install ramp from west lower level (back) doorway elevation to grade – Red Mill
  • Replacement of failed air conditioning chiller unit and associated work – Goff
  • Removal of the utility company original transformer in the basement and installation of new on-grade utility company transformer with new underground wiring to the building – Red Mill
  • Creation of gender-neutral toilet rooms with associated abatement, supply and waste piping, fixtures, finishes, etc. – Goff
  • Repair of exterior wall panels around Gym above the adjacent roofing – Goff
  • Reconstruction of large bus parking area paving – Transportation
  • Reconstruction of north area paving – Building & Grounds Shop
New bathroom at Green Meadow

New handicapped accessible bathroom at Green Meadow.

In Process

  • Replacement of plumbing fixtures with associated abatement, supply and waste piping, finishes, etc. in original group toilet rooms – Goff, Green Meadow and Red Mill
  • Provide daylighting controls on room lighting and replacement of failing occupancy energy management master controls on lighting – Goff, Green Meadow and Red Mill
  • Selected areas of exterior masonry repair – Goff and Red Mill
  • Replacement of plumbing fixtures with associated abatement, supply and waste piping, finishes, etc. in original group toilet rooms – Green Meadow and Red Mill

Summer 2021
Goff, Red Mill, Green Meadow

  • Green Meadow Elementary School
    • Re-roofing of older sections of roof membrane
    • Replacement of HVAC systems in office suites
    • Removal of the utility company original transformer in the basement and installation of new on-grade utility company transformer with new underground wiring to the building
  • Goff Middle School
    • Replacement of HVAC systems in office suites
    • Modifications to the Technology Suite spaces
    • Reconstruction of Home & Careers Suite spaces
    • Re-roofing of older sections of roof membrane
    • Reconstruction of service/north area paving
    • Expansion of parent-student drop-off area
Green Meadow cabinets and sink

New classroom cabinetry.

Summer 2021/Summer 2022
Columbia, Bell Top, DPS and Genet

  • Submitted Phase III project plans to NYS Education Department after Phase II is bid
  • Bell Top, DPS and Genet Elementary Schools
    • Reconstruction work similar to the elementary schools listed above
  • Columbia
    • Modifications to the Technology Suites
    • Modifications to the overhangs at the exterior entry doors
    • Artificial Turf Field Surface Replacement including drainage modifications